玻璃钢标志桩铺设施工要求
一、是在开工前编制施工组织设计及施工方案,施工进度计划,材料设备、成品、半成品等进场计划送监理审批后再交至业主,并在进场后抓紧做好项目划分单位工程、单元工程、工序工程。
First, it is to prepare the construction organization design and construction plan, construction progress plan, material and equipment, finished products, semi-finished products and other entry plans before the start of construction, and then submit them to the owner after submitting them to the supervision for approval. After entering the site, it is necessary to do a good job in dividing the project into unit projects, unit projects and process projects.
二、是开工前要先进行场地清理,包括开挖区的杂草、垃圾、不可利用的表土及其障碍物。应对测量控制点及放线位置进行校核,开挖边线应有足够数量的玻璃钢标志桩,并要注意防止移位、损坏。施工方需邀请村委和群众代表一同参与放线工作,避免发生不必要的矛盾,保证工程开工顺利进行。
2. Site cleaning should be carried out before construction starts, including weeds, garbage, unavailable topsoil and obstacles in the excavation area. It is necessary to check the position of control points and lay-out lines. There should be a sufficient number of FRP marking piles in the excavation side line, and attention should be paid to preventing displacement and damage. The construction party should invite the village committee and the people's representatives to participate in the wiring work, so as to avoid unnecessary contradictions and ensure the smooth start of the project.
三、是开挖和回填土方面:开挖基础的深度和宽度要符合按设计要求,如有异常现象应及时向监理、业主汇报,待做出处理决定后再继续施工。回填土要按照要求进行回填,否则一律不予验收。
3. Excavation and backfill: the depth and width of excavation foundation should meet the design requirements. If there are abnormal phenomena, it should report to the supervisor and the owner in time, and then continue construction after making treatment decisions. Backfill should be backfilled according to the requirements, otherwise it will not be accepted.
四、是隐蔽工程必须经监理及现场代表到现场核实、验收签证并拍照后,方可进行下一道工序。施工方必须将工程签证资料在相应工程结束后5天内完成并提交给业主。
Fourthly, the next working procedure can only be carried out after the supervision and site representative have come to the site to verify, check and accept the visa and take photos. The construction party must complete the project visa information and submit it it to the owner within 5 days after the completion of the corresponding project.
五、是砌体伸缩缝、沉降缝的要求:按设计部门提出的要求,砌体伸缩缝、沉降缝必须按设计要求预留,缝内充填材料需按设计要求使用沥青水泥砂浆,如未按设计要求完成的,一律要完善后才能验收。
5. Requirements for expansion joints and settlement joints of masonry: According to the requirements put forward by the design department, expansion joints and settlement joints of masonry must be reserved according to the design requirements. The filling materials in the joints need to use asphalt cement mortar according to the design requirements. If they are not completed according to the design requirements, they must be perfected before acceptance.
六 、是PE管材必须按照设计要求采购,所采购后PE管材的品牌、承载压力等规格参数必须与招投标文件一致。水泵、管材等设备材料到货后要及时通知监理和业主代表到现场抽样送技术监督局检测。使用前必须进行试运行实验并作好记录。
Sixth, PE pipes must be purchased according to the design requirements. The brand and bearing pressure of PE pipes after purchasing must be consistent with the bidding documents. After the arrival of pumps, pipes and other equipment and materials, the supervisor and the owner's representative should be notified in time to sample and send to the Technical Supervision Bureau for inspection. Trial operation experiments must be carried out and recorded before use.
七 、是施工方要确保做到施工过程资料与施工进度同步,保证过程资料的完整性和准确性。如施工过程资料不能与施工进度同步,发包人有权拒付工程进度款或结算款。
Seventh, the construction party should ensure that the construction process data and construction progress are synchronized, and the integrity and accuracy of the process data are guaranteed. If the construction process data can not be synchronized with the construction progress, the contractor has the right to refuse to pay the project progress or settlement.
八 、是施工方必须接受政府、村委、烟叶站和业主有关现场管理人员的工程质量监督。
Eighth, the construction party must accept the supervision of the quality of the project by the government, the village committee, the tobacco leaf station and the relevant field managers of the owners.
九是各施工方要高度重视施工过程中的安全工作,做到工程结束无大小事故。
Ninth, all construction parties should attach great importance to the safety work in the construction process, so that no major or minor accidents occur at the end of the project.